Panel schedule · MP-1

ALLENTOWN, PA

PPL

Ckt

Load

Amps

1-3

Main service, 3-phase

800A

4

Lighting panel, floor 1

225A

5

RTU mechanical feed

150A

6

Fire alarm & low voltage

20A

Full takeoff delivered with drawing markups

All 67 counties

Service area

24-72 hours

Standard turnaround

NEC under the UCC

Code baseline

Why contractors use us

Estimating built around how PA electrical actually gets priced

Electrical costs move on things a generic estimate misses - which utility a service connects to, whether a municipality has adopted its own NEC amendment, and whether low voltage and fire alarm scope is being tracked separately from power distribution. We build that into the takeoff instead of treating electrical as one blended trade cost.

Utility-aware service sizing

Service and interconnection requirements are checked against PECO, PPL, Duquesne Light, West Penn Power, or Met-Ed territory, whichever applies.

Circuit-level detail

Panel schedules, feeder sizing, and branch circuit counts are taken off directly from the one-line diagram and floor plans.

Low voltage tracked separately

Structured cabling, fire alarm, and security scope are priced as their own line items, never absorbed into a general electrical number.

Licensed-estimator review

Every takeoff is checked by a second estimator against the drawings before delivery.

Works your software

Accubid, McCormick, ConEst, Bluebeam, PlanSwift, or STACK - we estimate in the platform your team already reviews in.

24-72 hour turnaround

Standard takeoffs return in 24-72 hours, with rush service available ahead of a tight bid deadline.

Scope of Services Pennsylvania

What's included in an electrical estimate

Power, lighting, low voltage, and bid support are quantified as their own line items, from the one-line through change-order pricing.

EL-01

Power distribution & service

Main service equipment, switchgear, transformers, panels, feeders, and branch circuit wiring, sized and quantified from the one-line and panel schedules.

EL-02

Conduit, raceway & cable

Conduit runs, cable tray, wire, and cable counted by size and type, segmented by floor or area for accurate material pricing.

EL-03

Lighting & controls

Interior, exterior, and emergency lighting fixture counts, plus lighting control systems, taken off room by room.

EL-04

Low voltage & structured cabling

Data and communication cabling, network infrastructure, and AV rough-in quantified separately from power scope.

EL-05

Fire alarm, security & access control

Fire alarm devices, CCTV, access control, and security system components counted and priced as a dedicated system.

EL-06

Backup power & renewables

Generators, UPS systems, battery storage, solar electrical scope, and EV charging infrastructure takeoffs.

EL-07

Bid preparation & leveling

A formatted bid package for GC or owner submission, or a leveling worksheet for comparing incoming electrical subcontractor bids.

EL-08

Change order & addendum pricing

Fast re-takeoffs when an addendum or mid-project change order shifts electrical scope before your response is due.

Utility territory

Priced for the utility your project actually connects to.

Service and interconnection requirements differ between PECO, PPL, Duquesne Light, West Penn Power, and Met-Ed territory, and these are flagged during scope review.

PECO

Philadelphia & southeastern PA

Service and interconnection requirements are checked against PECO territory when the project connects there.

Southeastern PAPhiladelphia

PPL

Lehigh Valley & central-eastern PA

PPL Electric Utilities territory, including Allentown and the Lehigh Valley, is flagged during scope review.

Lehigh ValleyAllentown

Duquesne Light

Pittsburgh & Allegheny County

Duquesne Light service territory covers Pittsburgh and Allegheny County interconnection requirements.

PittsburghAllegheny County

West Penn / Met-Ed

Western & south-central PA

West Penn Power and Met-Ed territories cover western and south-central Pennsylvania regions.

West Penn PowerMet-Ed

Project segments

Residential, commercial, industrial & low voltage

Each segment is estimated around the systems and bid conditions that show up on that type of Pennsylvania job.

Residential

Single-family, custom homes, townhouses, and multi-family wiring, service upgrades, and fixture packages.

Commercial

Office, retail, restaurant, hotel, and school electrical systems sized for occupancy and code-required loads.

Industrial

Manufacturing and warehouse power distribution, high-capacity service, and plant lighting sized for production loads.

Low voltage & specialty

Structured cabling, fire alarm, security, AV, and renewable/EV charging systems as standalone estimating packages.

Code & utility reference

Checked against Pennsylvania's electrical rulebook

Planning reference only, not legal or code-compliance advice - confirm applicable requirements with your electrical engineer of record and local code official.

Statewide code

NEC as adopted under the PA UCC

The National Electrical Code, as adopted statewide under the Pennsylvania Uniform Construction Code, is the baseline reference for every takeoff.

Local amendments

Philadelphia & Pittsburgh amendments

Both cities administer their own electrical permitting and inspection process layered on top of the statewide code.

Inspection

PA L&I electrical inspection

Third-party and municipal code officials handle electrical inspection under the UCC framework; scope review confirms which agency applies.

Fire alarm

NFPA 72 fire alarm requirements

Fire alarm device layout and notification requirements are checked against NFPA 72 as adopted under the current code edition.

Energy code

Energy code lighting provisions

Lighting power density and control requirements under the adopted energy code are verified for commercial and multifamily projects.

Labor

Pennsylvania Prevailing Wage Act

Publicly funded electrical work is priced against the county-specific prevailing wage schedule from the PA Department of Labor & Industry.

Our process

From drawing set to bid-ready estimate

Six steps from the one-line, panel schedules, and floor plans you send to a priced estimate and marked-up takeoff drawings.

01

Drawings submitted

Send the one-line diagram, panel schedules, and floor plans, along with any addenda.

02

Utility & jurisdiction check

We confirm the Pennsylvania utility territory and any local NEC amendments that apply to the project.

03

Quantity takeoff

Every circuit, fixture, and device is measured and counted directly on the drawings, organized by system.

04

Pricing applied

Current Pennsylvania material and labor rates are applied line by line, with equipment and markup broken out separately.

05

Internal review

A second estimator checks quantities and pricing against the drawing set before delivery.

06

Delivery

You receive the estimate and the marked-up takeoff drawings, with a walkthrough call available if needed.

Sample output

What an electrical estimate looks like

Shortened excerpt from a 4-story office building in Allentown, PPL Electric Utilities territory.

Sample excerpt - 4-story office, Allentown

PPL ELECTRIC UTILITIES TERRITORY

Excerpt

800A main service & switchgear

1

LS

$118,000

$62,000

3/4" EMT conduit

14,200

LF

$29,820

$44,020

LED lighting fixtures

460

EA

$96,600

$41,400

Fire alarm devices

180

EA

$32,400

$27,000

Structured cabling, Cat6A

9,600

LF

$14,400

$19,200

Subtotal, lines shown

Material $291,220

Labor $193,620

Software & pricing sources

Tools behind the takeoff

Accubid, McCormick, ConEst, Bluebeam Revu, PlanSwift, and STACK, paired with current Pennsylvania regional pricing.

Accubid

Electrical estimating

McCormick

Electrical estimating

ConEst

Electrical estimating

Bluebeam Revu

Drawing markup & takeoff

PlanSwift

Quantity takeoff

STACK

Quantity takeoff

Pennsylvania material & labor pricing

Regional pricing source

Coverage areas

Electrical estimating across Pennsylvania

All 67 counties, with local utility and permitting differences built into every estimate.

Southeast PA

  • Philadelphia
  • Reading
  • Lancaster
  • Bethlehem
  • Allentown

Southwest & Central PA

  • Pittsburgh
  • Harrisburg
  • Altoona
  • State College
  • Carlisle

Northern PA

  • Erie
  • Scranton
  • Wilkes-Barre
  • Williamsport
  • York

Accuracy & review

Checked before it reaches your bid.

Utility territory, quantities, and pricing are reviewed against the drawing set before the estimate and marked-up takeoff are delivered.

A second estimator checks the takeoff

Every takeoff is checked by a second estimator against the drawings before delivery. Quantities and pricing are reviewed against the drawing set.

Utility territory confirmed first

We confirm the Pennsylvania utility territory and any local NEC amendments that apply before quantities are priced.

Low voltage kept as its own number

Structured cabling, fire alarm, and security scope are priced as their own line items, never absorbed into a general electrical number.

Marked-up drawings come with the estimate

You receive the estimate and the marked-up takeoff drawings, with a walkthrough call available if needed.

From Pennsylvania clients

What electrical contractors say

Contractors in the Lehigh Valley, Pittsburgh, and Harrisburg on utility territory, low voltage line items, and bid-day turnaround.

“They flagged that our Allentown project sat in PPL territory before we'd even asked. Saved us a call to the utility mid-bid.”

Owner, Electrical Subcontractor - Lehigh Valley

“Fire alarm and low voltage came back as separate line items instead of buried in the power number. Made our proposal much easier to defend.”

Chief Estimator, Commercial Electrical Contractor - Pittsburgh

“Turnaround was fast enough that we could actually double-check the panel schedule takeoff before submitting our bid.”

Project Manager, Design-Build Electrical - Harrisburg

What affects your cost

Pricing factors for electrical estimating

Estimating time follows project size, utility territory, low voltage scope, drawing completeness, and the turnaround you need.

01

Project size & system count

A residential service upgrade prices very differently than a multi-system commercial or industrial electrical package.

02

Utility territory

Service and interconnection requirements vary between PECO, PPL, Duquesne Light, and other Pennsylvania utilities.

03

Low voltage complexity

Fire alarm, security, and structured cabling scope adds separate takeoff time beyond standard power distribution.

04

Drawing set completeness

A full one-line diagram and panel schedules take off faster than a design-build set still missing final equipment specs.

05

Turnaround required

Rush requests ahead of a bid deadline are quoted separately from our standard 24-72 hour delivery window.

Request a quote

Send your Pennsylvania electrical set

Share the one-line diagram, panel schedules, and floor plans, along with the utility territory and bid deadline. We'll confirm scope and turnaround before takeoff starts.

  • Full takeoff delivered with drawing markups
  • Priced against Pennsylvania labor rates and utility territory
  • Standard turnaround of 24-72 hours
  • Delivered in Accubid, McCormick, ConEst, Bluebeam, PlanSwift, or STACK